@startgantt projectscale weekly [Community informed of major release] as [ci] lasts 1 day [WMDA develops apis] as [WMDA Devdev] requires 17 weeks [New apis deployed to test environment] as [test] happens at [WMDA develops apisdev]'s end [Community preparation, development and testing] as [comm prep] requires 25 weeks [Community ready to receive via new apis] as [comm rec] happens at [comm prep]'s end [apis deployed to prod] as [prod] requires 2 weeks [prod] starts after [comm rec]'s end [Community may send using new apis] as [new] happens at [prod]'s end [Community supports both versions] as [both] requires 4 weeks [both] starts after [new]'s end [Old apis deprecated] happens after [both]'s end @endgantt |