PlantUML Macro
@startgantt
projectscale weekly
[Community informed of major release] as [ci] lasts 1 day
[WMDA develops apis] as [WMDA Devdev] requires 17 weeks
[New apis deployed to test environment] as [test] happens at [WMDA develops apisdev]'s end
[Community preparation, development and testing] as [comm prep] requires 25 weeks
[Community ready to receive via new apis] as [comm rec] happens at [comm prep]'s end
[apis deployed to prod] as [prod] requires 2 weeks
[prod] starts after [comm rec]'s end
[Community may send using new apis] as [new] happens at [prod]'s end
[Community supports both versions] as [both] requires 4 weeks
[both] starts after [new]'s end
[Old apis deprecated] happens after [both]'s end
@endgantt