PlantUML Macro
@startgantt
title Major Releases of Match-Connect APIs (example schedule)
projectscale weekly
[Community informed of major release] as [ci] lasts 1 day
[WMDA develops apisAPIs] as [WMDA dev] requireslasts 17120 weeksdays
[apisAPIs deployed to test] as [test] happens at [WMDA dev]'s end
[Community preparation, development and testing] as [comm prep] requireslasts 25180 weeksdays
[Community ready to receive via new apis] as [comm rec] happens at [comm prep]'s end
[apisAPIs deployed to prod] as [prod] requireslasts 215 weeksdays
[prod] starts after [comm rec]'s end
[Community may send using new apisAPIs] as [new] happens at [prod]'s end
[Community supports both versions] as [both] requireslasts 430 weeksdays
[both] starts after [new]'s end
[Old apisAPIs deprecated] as [dep] happens after [both]'s end
[End] happens 364 days after [ci]'s end
@endgantt