@startgantt
title Major Releases of Match-Connect APIs (example schedule)
projectscale weekly
[Community informed of major release] as [ci] lasts 1 day
[WMDA develops APIs] as [WMDA dev] lasts 120 days
[APIs deployed to test] as [test] happens at [WMDA dev]'s end
[Community preparation, development and testing] as [comm prep] lasts 180 days
[Community ready to receive via new apis] as [comm rec] happens at [comm prep]'s end
[APIs deployed to prod] as [prod] lasts 15 days
[prod] starts after [comm rec]'s end
[Community may send using new APIs] as [new] happens at [prod]'s end
[Community supports both versions] as [both] lasts 30 days
[both] starts after [new]'s end
[Old APIs deprecated] as [dep] happens after [both]'s end
[End] happens 364270 days after [ci]'s end
@endgantt

...